25 days before the relocationScene 3 / 13
Completed projects are transferred first.
The data of projects completed over the past few years is mostly final.
In contrast, the materials of projects currently in progress change or are newly created every day.
The person in charge decides the transfer order based on the business characteristics of the data.
DATA TRANSFER PLAN
Not all business data needs to be transferred at the same time.
- Completed projectsArchived projectsPast work materials whose content is final are transferred first.58 TBTransfer scheduleFrom 25 days before
- Shared work materialsShared technical resourcesMaterials used to validate the work environment at the new site are prepared.10 TBTransfer scheduleIn parallel with the transfer of existing projects
- Projects in progressActive projectsCurrent materials are transferred first, and materials added or changed afterwards are reflected separately.18 TBTransfer scheduleAdditional transfers after the initial transfer, until the last working day
Studio, Flows
| Flow name | Size | Status |
|---|
| Archived projects | 58 TB | Running |
| Technical resources | 10 TB | Scheduled |
| Active projects | 18 TB | Scheduled |
| Additional project files | Variable | Ready |
Live contextNow
25 days beforeData transfer
Completed projects are transferred first.To avoid affecting current work, past projects and test records that are unlikely to change are transferred to the new site first.
- Total transfer scope86.00 TB
- Data transferred0.00 TB
- Remaining data86.00 TB
- Existing center
- Normal operation
- New center
- Started receiving data
- Next task
- Transferring past business data
INITIAL DATA TRANSFER0 TB
Based on the initial 86TB scope Next story, 18 days before the relocationNew data is generated even while data is being transferred. →18 days before the relocationScene 4 / 13
New data is generated even while data is being transferred.
A week has passed since the data transfer started.
Files from the existing site are being delivered to the new site, but testing and analysis work also continues at the existing site.
The size of the data newly generated over the past week is 800GB.
The total transfer scope checked a week ago and the range of data that must be transferred now are no longer the same.
BUSINESS CONTINUES DURING TRANSFER
Shrinking transfer targets and continuously growing business data
Total data to be transferredData delivered to the new site
D-25D-24D-23D-22D-21D-20D-19D-18
- Initial transfer scope
- 86 TB
- Newly generated data
- 800 GB
- Transfer complete
- 35 TB
CURRENT TECHNICAL CENTERWork still in progress today- Product durability tests
- Component quality validation
- Test result analysis
NEW TECHNICAL CENTERRECEIVED DATA35 TBBusiness data transfer in progress- Receiving past projects
- Shared work materials to be received
- Preparing the new work environment
Live contextNow
18 days beforeData transfer
Work continues while the data is being transferred.New test results and analysis materials are being generated at the existing site. Data transfer to the new site runs in parallel.
- Total transfer scope86.80 TB
- Data transferred35.00 TB
- Remaining data51.80 TB
- Existing center
- 38 projects in progress
- New center
- Receiving data
- Next task
- Transferring active projects
INITIAL DATA TRANSFER35 TB
Based on the initial 86TB scope Next story, 14 days before the relocationThere are materials the new site needs first. →14 days before the relocationScene 5 / 13
There are materials the new site needs first.
At the new technical support center, the test equipment has been installed and the work applications are being validated.
However, the installation of equipment alone is not enough to confirm that existing work can be performed normally.
Materials on products tested in the past, standard test procedures and actual measurement data are needed.
The person in charge transfers the materials needed for validation separately before the full data transfer is finished.
EARLY ACCESS FOR WORKPLACE VALIDATION
Not all the data has arrived yet, but some work can already be prepared.
Request to validate the test environment at the new siteThe materials below are needed for the test equipment validation starting next week.
Standard_Test_Procedures/12 GBReference_Test_Data/180 GBEquipment_Configuration/8 GBSample_Engineering_Projects/120 GB
Data requested for priority transfer320 GB
RunsCurrent transfers
- Historical project transferRunning
- Workplace validation files320GB transfer completeCompleted
The new site starts validating the work environment using the materials it has received. The transfer of the existing data also continues.
Live contextNow
14 days beforeData transfer
There are materials the new site needs first.The new technical support center receives the materials needed for test equipment validation separately, before the full data transfer is complete. The transfer of existing data continues.
- Total transfer scope86.80 TB
- Data transferred60.50 TB
- Remaining data26.30 TB
- Existing center
- 38 projects in progress
- New center
- Receiving validation materials first
- Next task
- Complete the existing data transfer
INITIAL DATA TRANSFER60 TB
Based on the initial 86TB scope Next story, 10 days before the relocationThe transfer of the originally planned data is complete. →10 days before the relocationScene 6 / 13
The transfer of the originally planned data is complete.
The 86TB of data identified at the start of the relocation has been delivered to the new site.
However, work at the existing site continues for ten more days.
Some of the files already delivered have changed again, and new files have also been created.
Completing the full data transfer does not mean the relocation is complete.
INITIAL TRANSFER COMPLETED
Work that remains even after the initial data transfer
Initial transfer scope86 TBTransfer complete
Data added since the transfer started1.9 TBNew materials not included in the initial transfer scopeAdditional transfer
Work materials that need to be transferred additionally
| Project | Changes | Size |
|---|
| Product A | New test results | 480 GB |
| Product B | Additional analysis data | 620 GB |
| Product C | Quality validation data | 340 GB |
| Shared work materials | New technical materials | 160 GB |
| Other projects | New business data | 300 GB |
Total size of new materials1.90 TB
Live contextNow
10 days beforeData transfer
The transfer of the originally planned 86TB of data is complete.The transfer of the files in the initial scope is complete. Materials created or changed at the existing site after that are checked and transferred separately.
- Total transfer scope87.90 TB
- Data transferred86.00 TB
- Remaining data1.90 TB
- Existing center
- Normal operation
- New center
- Existing data secured
- Next task
- Transferring added and changed materials
INITIAL DATA TRANSFER86 TB
Based on the initial 86TB scope Next story, 7 days before the relocationExisting projects are opened at the new site. →